Westridge Reclad & Fire Alarm Replacement
Remove and replace exterior brick, and replace fire alarm system at Westridge Elementary School.
Project Team
Dave Kruger
Project Manager
Project Updates
March 2026 Status Summary:
- Five bids were received on March 19
- 2KG Contractors was the lowest, responsive bidder
- A Notice of Intent to Award was sent out on March 23
- Contract is under review
Project Manager’s Notes:
- Project start date scheduled for June 15
February 2026 Status Summary:
- The Invitation to Bid was released on February 18
- A mandatory pre-bid site walk was held on February 25
- Bids are due on March 19
- Project is scheduled for the summer of 2026
Project Manager’s Notes:
- Soderstrom Architects has submitted plans to the city for a permit
- Precision Images has plans & specifications for contractors to obtain
January 2026 Status Summary:
- Soderstrom Architects has reviewed the previous drawings and specifications
- 100% Design Development drawings were provided on January 16, 2026
- T.M. Rippey Consulting Engineers has been contracted to do structural engineering
- Landis Consulting has been contracted for fire alarm design
- Project is scheduled for the summer of 2026
Project Manager’s Notes:
- Structural site walk was on January 14, 2026
- Fire alarm site walk was on January 15, 2026
December 2025 Status Summary:
- Soderstrom Architects has reviewed the previous drawings and specifications
- 100% SD drawings were provided on December 24, 2025
- Project is scheduled for the summer of 2026
Project Manager’s Notes:
- The first sitewalk was on December 11, 2025
- Second site walk is scheduled for January 15, 2026
November 2025 Status Summary:
- The District has executed a contract with the original design firm to update the construction documents and incorporate additional scope
- A kickoff meeting is scheduled to review the detailed scope of work, establish schedule milestones, and confirm budget parameters
- Incorporate additional work identified by the District since the original 2019 design
- Ensure compliance with the current building codes and standards
- Address any changes in site conditions or District requirements
- Updated construction documents are targeted for completion by January 2026, followed immediately by submission for building permit approval.