Westridge Reclad & Fire Alarm Replacement

Remove and replace exterior brick, and replace fire alarm system at Westridge Elementary School.

Project Team


Dave Kruger
Project Manager

Project Updates


March 2026 Status Summary:

  • Five bids were received on March 19
  • 2KG Contractors was the lowest, responsive bidder
  • A Notice of Intent to Award was sent out on March 23
  • Contract is under review
Project Manager’s Notes:
  • Project start date scheduled for June 15

February 2026 Status Summary:

  • The Invitation to Bid was released on February 18
  • A mandatory pre-bid site walk was held on February 25
  • Bids are due on March 19
  • Project is scheduled for the summer of 2026
Project Manager’s Notes:
  • Soderstrom Architects has submitted plans to the city for a permit
  • Precision Images has plans & specifications for contractors to obtain

January 2026 Status Summary:

  • Soderstrom Architects has reviewed the previous drawings and specifications
  • 100% Design Development drawings were provided on January 16, 2026
  • T.M. Rippey Consulting Engineers has been contracted to do structural engineering
  • Landis Consulting has been contracted for fire alarm design
  • Project is scheduled for the summer of 2026
Project Manager’s Notes:
  • Structural site walk was on January 14, 2026
  • Fire alarm site walk was on January 15, 2026

December 2025 Status Summary:

  • Soderstrom Architects has reviewed the previous drawings and specifications
  • 100% SD drawings were provided on December 24, 2025
  • Project is scheduled for the summer of 2026
Project Manager’s Notes:
  • The first sitewalk was on December 11, 2025
  • Second site walk is scheduled for January 15, 2026

November 2025 Status Summary:

  • The District has executed a contract with the original design firm to update the construction documents and incorporate additional scope
  • A kickoff meeting is scheduled to review the detailed scope of work, establish schedule milestones, and confirm budget parameters
    • Incorporate additional work identified by the District since the original 2019 design
    • Ensure compliance with the current building codes and standards
    • Address any changes in site conditions or District requirements
  • Updated construction documents are targeted for completion by January 2026, followed immediately by submission for building permit approval.