Science Labs Project Updates

March 2025


LOHS Status Summary:
  • Renovation Construction Phase 2 start date is June 16, 2025
  • Construction Phase 2 will include a new AHU(air handling unit), the remaining classrooms, and common areas. The AHU has been ordered with an expected delivery in July 2025
  • The contractor will perform some of the cabinet work over spring break
  • Project Manager’s Notes:
    • The contractor is working on Phase 1 punch list items and submittals for Phase 2
    • New exhaust fans have been installed on the roof
LHS Status Summary:
  • Phase 1 construction complete
  • Project Manager’s Notes:
    • The contractor is working on the final punch list items
    • Air balancing is being adjusted during spring break
    • Overhead electrical outlet connections are completed in two classroom lab areas
    • New exhaust fans have been installed on the roof
    • New AHU-11 has been installed and is operational
LHS Phase 2 Status Summary:
  • Construction Phase 2 start date will be June 16, 2025
  • First Cascade is providing submittals for approval to place advance orders
  • First Cascade will be working during spring break on plumbing pipe scoping and jetting
  • Project Manager’s Notes:
    • OAC meetings are scheduled every two weeks, on Wednesdays at 2:00 p.m.

February 2025


science lab LHS logo sign
LOHS Status Summary:
  • Renovation Construction Phase 2 start date is June 16, 2025
  • Construction Phase 2 will include a new AHU(air handling unit), the remaining classrooms, and common areas. The AHU has been ordered with expected delivery in July 2025
  • The contractor will perform some of the cabinet work over spring break
  • Project Manager’s Notes:
    • The contractor is working on Phase 1 punch list items and submittals for Phase 2
    • New exhaust fans have been installed on the roof
LHS Status Summary:
  • Phase 1 construction complete
  • Project Manager’s Notes:
    • The contractor is working on the final punch list items
    • New metal lab tables with phenolic countertops and electrical outlets are installed in two classrooms
  • Construction Phase 2 start date will be June 16, 2025
  • First Cascade is providing submittals for approval to place advance orders
  • Project Manager’s Notes:
    • OAC meetings are scheduled every two weeks, Wednesdays at 2:00 p.m.

January 2025


LOHS Status Summary:
  • Renovation Construction Phase 2 start date is June 16, 2025
  • Construction Phase 2 will include a new AHU(air handling unit), the remaining classrooms, and common areas. The AHU has been ordered with expected delivery in July 2025
LHS Status Summary:
  • Phase 1 construction complete
  • Construction Phase 2 start date will be June 16, 2025
  • Project submittals are ongoing

September 2024


science lab lohs logo
LOHS Status Summary:
  • Construction Phase 1 start date was June 17, 2024, and included renovation of 4 science classrooms and the common areas
  • MEP rough-in and new terminal units are completed
  • Ceilings are re-installed
  • Wood ceiling at elevator lobby nearing completion. LO logo is installed with a backlight
  • New flooring is installed in four classrooms and the main corridor
  • New base cabinets with new countertops, sinks, and faucets installed
  • Construction Phase 2 will be the summer of 2025 and will consist of a new AHU (air handling unit) and the remaining classroom renovations
LHS Status Summary:
  • Construction Phase 1 start date was June 17, 2024, and consisted of renovation to 4 Science classrooms, restrooms, and staff prep areas
  • MEP rough-in and new AHU (air handling unit) have been installed
  • Ceilings are re-installed with new light fixtures
  • Entry stairs to the Science Department have wood paneling on the walls and new wood slat ceilings
  • Restroom areas have been redesigned with new fixtures, toilet accessories, and tile floors and walls
  • New flooring is installed in four classrooms and staff prep areas
  • New base and upper cabinets with new countertops, sinks, and faucets are installed
  • A Life Skills area has been created near the counseling area; this area consists of a kitchen, washer & dryer, and ADA restroom
  • Construction Phase 2 will take place during the summer of 2025 and will consist of renovation of the four remaining science classrooms

December 2023


Project Status:

  • Meetings with LOSD administration, LHS science teachers, Bond Department, and Arcadis Architects are ongoing. More meetings are being scheduled to define design direction and scope
  • A two-part phasing plan is being discussed and reviewed. Phase 1: remodel and upgrades to existing classrooms
    Phase 2: STEM hub and extended learning spaces

November 2023

Project Status:

  • Meetings with LOSD administration, LHS science teachers, Bond Department, and Arcadis Architects are ongoing. More meetings are being scheduled to define design direction and scope
  • The renovation projects at both high schools are planned to bid to GCs in the early spring of 2024; construction scheduled for summer of 2024
  • A two-part phasing plan is being discussed and reviewed. Phase 1 will consist of a remodel and upgrades to existing classrooms. Phase 2 will consist of STEM hub and extended learning spaces

October 2023

Project Status:

  • Meetings with LOSD administration, LOHS science teachers, Bond Department, and Arcadis Architects are ongoing. More meetings are being scheduled to define design direction and scope

September 2023

Project Status:

  • Meetings with LOSD administration, Bond Department, and ArcadisĀ  IBI Group are ongong. More meetings are being scheduled to define design direction and scope
  • The renovation projects at both high schools are planned to bid to GCs in the early spring of 2024; construction scheduled for summer of 2024
  • A two-part phasing plan is being discussed and reviewed. Phase 1 will consist of a remodel and upgrades to existing classrooms. Phase 2 will consist of extended learning spaces and additional upgrades

August 2023

Project Status:

  • There have been two meetings with LOSD administration, Bond Department, and ArcadisĀ  IBI Group. More meetings are being scheduled to define design direction and scope
  • The renovation projects at both high schools are planned to bid to GCs in the early spring of 2024; construction scheduled for summer of 2024
  • A possible phasing may take place with work scheduled for completion over two summers