Pool Field House
The existing pool located at the Lake Oswego campus will be decommissioned and renovated into a large multipurpose space. With minor cosmetic improvements, such as paint and siding repairs, the facility will also receive a gymnasium floor and basketball goals. The project will also include some lighting replacement and plumbing fixture replacement.
Project Team
Dave Kruger
Project Manager
Jamie Harnish
Project Coordinator
Project Updates
March 2025 Status Summary:
- Construction is tentatively scheduled for the summer of 2025
- 100% Bid Documents went out to bid on January 31, bids due February 27
- Nine general contractors submitted bids. Bids range from $837,000 to $1,349,465
- The lowest responsive bidder was First Cascade Corporation at $837,000. A Notice of Intent to Award was distributed on March 7, 2025
- BBL Architects submitted permit documents to the city on January 31, 2025
Project Manager’s Notes:
- Geotechnical construction observation services have been contracted with Carlson Geotechnical
- Carlson Geotechnical has revised its memorandum and provided a draft report for the design team review
February 2025 Status Summary:
- Construction is tentatively scheduled for the summer of 2025
- 100% Bid Documents went out to bid on January 31, bids due February 27
- Three addendums have been submitted
- BBL Architects submitted permit documents to the city on January 31, 2025
Project Manager’s Notes:
- Environmental and abatement survey services completed by PBS Engineering and Environmental
- Geotechnical construction observation services have been contracted with Carlson Geotechnical
- Carlson Geotechnical has revised its memorandum and provided a draft report for the design team review
January 2025 Status Summary:
- Construction is tentatively scheduled for the summer of 2025
- 100% Bid Documents went out to bid on January 31, bids due February 27
- BBL Architects submitted permit documents to the city on January 31, 2025
Project Manager’s Notes:
- Environmental and abatement survey services completed by PBS Engineering and Environmental
- Geotechnical construction observation services have been contracted with Carlson Geotechnical
December 2024 Status Summary:
- 75% CD Drawings are in review
- BBL Architects continues with code review and Land Use considerations
- Construction is tentatively scheduled for the summer of 2025
Project Manager’s Notes:
- PBS has performed abatement surveys and has sent samples for testing
- Carlson Geotechnical has revised its memorandum and provided a draft report for the design team review
October 2024 Status Summary:
- Pool is planned to be decommissioned
- Pool area would be infilled and leveled
- Pool and surrounding area would be topped with gym flooring
- Building would receive other minor improvements like LED lighting replacements
Project Manager’s Notes:
- Designer is being brought on board
- Beginning code review and Land Use considerations
- Construction would start some time after the LORAC project is complete