  • Greenhouse installation was completed on February 12
  • On February 24, the City of Lake Oswego inspected and closed out all permits, including mechanical, electrical, and building permits
  • School staff and students can begin utilizing the new greenhouse

January 2025


greenhouse construction next to school
Status Summary:
  • New garden areas, including garden beds and the circle garden, and irrigation are complete
  • Land use and building permit applications have been approved
  • The District has procured the required contractors to complete the scope of work, including an excavator and concrete contractor to build the new slab and a greenhouse installer to build the pre-manufactured structure. An electrical contractor will complete the final scope to provide power to the greenhouse. All contractors are under contract with the District
  • Construction began Monday, January 20, and completion is targeted for February 14
  • The schedule status has been modified to Caution due to delays experienced during the permitting process. This has extended construction by a few weeks. The District does not expect any additional delays, and construction completion is targeted for the end of February

December 2024


greenhouse rendering next to lms
Status Summary:
  • New garden areas, including garden beds and the circle garden, and irrigation are complete
  • Greenhouse assembly pending permitting process (Land Use & Building) through the City of Lake Oswego. The district is expecting approval and to begin construction by mid-January
  • Pending scope includes concrete slab for the greenhouse, assembly of greenhouse and installation of mechanical equipment, electrical scope including routing of power to new greenhouse connections

November 2024


outdoor learning space with tables next to school
Status Summary:
  • New Garden areas, including garden beds and the circle garden, and irrigation complete
  • Greenhouse assembly pending permitting process (Land Use & Building) through the City of Lake Oswego. The district is targeting December 2024 to begin construction
  • Pending scope includes concrete slab for the greenhouse, assembly of greenhouse and installation of mechanical equipment, electrical scope including routing of power to new greenhouse connections

August 2024


circle garden
Status Summary:
  • Circle garden, irrigation, and plantings completed
  • New picnic tables and benches received
  • Greenhouse installation and electrical scope pending permitting approval