Project Updates
Playground & Garden Update: December 2023
Status Summary:
- Westridge Elementary School: Playground & Gardens
- determining scope of work
- contractor procurement - Lakeridge Middle School: Outdoor Learning Space - Greenhouse/Gardens
- design phase: coordinating with staff to meet school needs
Palisades Renovations: December 2023
Project Status:
- Substantial Completion achieved September 18, 2023
- General Contractor finalizing O&Ms
Playground & Garden Update: November 2023
Project Status:
- Westridge Elementary School
- Playground & Gardens
* determining scope of work
* contractor procurement - Lakeridge Middle School
- Outdoor Learning Space: greenhouse/gardens
* design phase: coordinating with staff to meet school needs
Palisades Renovations: November 2023
Project Status:
Phase 1
- Substantial Completion achieved September 18, 2023
- General Contractor finalizing:
-commissioning
-closeout documents
Phase 2:
- Design - Construction Documents in progress
- Renovations scheduled for summer of 2024
October 2023
Palisades Renovations: October 2023
Project Status:
- Substantial Completion achieved September 18, 2023
- General Contractor finalizing:
-punchlist open items
-commissioning
-closeout documents
Playground & Garden Upgrades: October 2023
Project Status:
- Native garden at Palisades Elementary
- final planting completed on October 12, 2023 - Garden beds at Palisades Elementary
- complete - Playground equipment at Palisades Elementary
- complete
Playground & Garden Upgrades: September 2023
Palisades Renovations: September 2023
Project Status:
Recently completed tasks include:
-electrical: connections to new equipment and installation of
new panels
-installation of future chiller lines
-kitchen equipment installation
-conduit lines and duct work insulation and labeling
-re-roofing and sheet metal work for flashings and gutters
Pending tasks include:
-split system controls and start up
-training
-commissioning
-punchlist items
-O&Ms
Phase 2 renovations scheduled for summer of 2024
Playground & Garden Upgrades: September 2023
Project Status:
Native garden at Palisades Elementary
- majority of work has been completed
- planting is the only pending work and is
dependent on cooler weather
- estimated completion date is October 13, 2023
Garden beds at Palisades Elementary
- gravel pad and bed installation have been completed
- estimated completion date for bed irrigation is
October 29, 2023
Playground equipment at Palisades Elementary
- playground installation has been completed
Palisades Renovations: August 2023
Project Status:
Recently completed tasks include:
- gym/physical education office: seismic upgrades, wall painting, clean-up, gym office carpet installed
- classroom #31: carpet, paint, clean-up
- hallway: seismic upgrades by gym wall, painting, clean-up
- new transformer and switchgear
- kitchen: new flooring, walk-in cooler & freezer, kitchen hood installed
Current site activity includes:
- mechanical equipment start-up
- electrical: connections to new equipment and installation of new panels
- installation of future chiller lines
- kitchen equipment installation
- re-roofing
Phase 2 renovations scheduled for summer of 2024
Playground & Garden Upgrades: August 2023
Project Status:
- Native garden at Palisades Elementary
- majority of work has been completed
- planting is the only pending work and is dependent
on cooler weather
- estimated completion date is October 20, 2023 - Garden beds at Palisades Elementary
- gravel pad and bed installation has been completed
- irrigation connection is pending
- end of August 2023 completion - Playground equipment at Palisades Elementary
- playground installation has been completed
June 30, 2023
Project Status
- Contractor fully mobilized to the school as of June 14
- Abatement work in roof, boiler room, and kitchen has been
completed - Saw cutting and removal of slab for underground
connections in kitchen area has been completed - Seismic upgrades of gym in progress
- Reroof of gym and kitchen continues
- Mechanical scope continues in boiler room and kitchen
- Phase 2 renovations scheduled for summer of 2024
- Native garden at Palisades Elementary
- Grasstains, LLC began construction of the native garden on June 27
- Estimated completion date is July 21, 2023 - Garden beds at Palisades Elementary
- district is gathering bids from contractors to complete the construction of the gravel pad required for the garden beds
- garden beds will be ready to install by end of August 2023 - Playground equipment at Palisades Elementary
- playground equipment has been ordered - delivery estimated for July 12
- installation of equipment scheduled for the end of July 2023
Native Garden Under Construction