Project Updates

Playground & Garden Update: December 2023

Status Summary:

  • Westridge Elementary School: Playground & Gardens
    - determining scope of work
    - contractor procurement
  •  
  • Lakeridge Middle School: Outdoor Learning Space - Greenhouse/Gardens
    - design phase: coordinating with staff to meet school needs

Palisades Renovations: December 2023

Project Status:

  • Substantial Completion achieved September 18, 2023
  • General Contractor finalizing O&Ms

Playground & Garden Update: November 2023

Project Status:

  • Westridge Elementary School
    - Playground & Gardens
      * determining scope of work
      * contractor procurement
  • Lakeridge Middle School
    - Outdoor Learning Space: greenhouse/gardens
       * design phase: coordinating with staff to meet school needs

Palisades Renovations: November 2023

Project Status:

Phase 1

  • Substantial Completion achieved September 18, 2023
  • General Contractor finalizing:
    -commissioning
    -closeout documents

Phase 2:

  • Design - Construction Documents in progress
  • Renovations scheduled for summer of 2024

October 2023

Palisades Renovations: October 2023

Project Status:

  • Substantial Completion achieved September 18, 2023
  • General Contractor finalizing:
    -punchlist open items
    -commissioning
    -closeout documents

Playground & Garden Upgrades: October 2023

Project Status:

  • Native garden at Palisades Elementary
    - final planting completed on October 12, 2023
  • Garden beds at Palisades Elementary
    - complete
  • Playground equipment at Palisades Elementary
    - complete

 

Playground & Garden Upgrades: September 2023

Palisades Renovations: September 2023

Project Status:

Recently completed tasks include:

-electrical: connections to new equipment and installation of
new panels
-installation of future chiller lines
-kitchen equipment installation
-conduit lines and duct work insulation and labeling
-re-roofing and sheet metal work for flashings and gutters

Pending tasks include:

-split system controls and start up
-training
-commissioning
-punchlist items
-O&Ms

Phase 2 renovations scheduled for summer of 2024

Playground & Garden Upgrades: September 2023

Project Status:

Native garden at Palisades Elementary
- majority of work has been completed
- planting is the only pending work and is
  dependent on cooler weather
- estimated completion date is October 13, 2023

Garden beds at Palisades Elementary
- gravel pad and bed installation have been completed
- estimated completion date for bed irrigation is
  October 29, 2023

Playground equipment at Palisades Elementary
- playground installation has been completed

Palisades Renovations: August 2023

Project Status:

Recently completed tasks include:
- gym/physical education office: seismic upgrades, wall painting, clean-up, gym office carpet installed
- classroom #31: carpet, paint, clean-up
- hallway: seismic upgrades by gym wall, painting, clean-up
- new transformer and switchgear
- kitchen: new flooring, walk-in cooler & freezer, kitchen hood installed

Current site activity includes:
- mechanical equipment start-up
- electrical: connections to new equipment and installation of new panels
- installation of future chiller lines
- kitchen equipment installation
- re-roofing

Phase 2 renovations scheduled for summer of 2024

Playground & Garden Upgrades: August 2023

Project Status:

  • Native garden at Palisades Elementary
    - majority of work has been completed
    - planting is the only pending work and is dependent
      on cooler weather
    - estimated completion date is October 20, 2023
  • Garden beds at Palisades Elementary
    - gravel pad and bed installation has been completed
    - irrigation connection is pending
    - end of August 2023 completion
  • Playground equipment at Palisades Elementary
    - playground installation has been completed

 

June 30, 2023

Project Status

  • Contractor fully mobilized to the school as of June 14
  • Abatement work in roof, boiler room, and kitchen has been
    completed
  • Saw cutting and removal of slab for underground
    connections in kitchen area has been completed
  • Seismic upgrades of gym in progress
  • Reroof of gym and kitchen continues
  • Mechanical scope continues in boiler room and kitchen
  • Phase 2 renovations scheduled for summer of 2024
  • Native garden at Palisades Elementary
    - Grasstains, LLC began construction of the native garden on June 27
    - Estimated completion date is July 21, 2023
  • Garden beds at Palisades Elementary
    - district is gathering bids from contractors to complete the construction of the gravel pad required for the garden beds
    - garden beds will be ready to install by end of August 2023
  • Playground equipment at Palisades Elementary
    - playground equipment has been ordered - delivery estimated for July 12
    - installation of equipment scheduled for the end of July 2023

Native Garden Under Construction

Native Garden under construction

 

 

Native Garden under construction