LOHS Roof Replacement
During the summer of 2026, the first phase of the roof replacement project at Lake Oswego High School is scheduled to begin.
The scope of work includes two phases, scheduled for the summers of 2026 and 2027, that will result in the complete removal and replacement of the school's roof.
Project Team
Dave Kruger
Project Manager

Project Updates
March 2026 Status Summary
- Six bids were received on February 26
- Notice of Intent to Award was sent out to Fulcrum Construction on March 4
- The contract is fully executed, and a Notice to Proceed was sent on March 17
- A Pre-construction meeting was held on March 24
Project Manager’s Notes:
- Project Phase 1 construction scheduled to begin June 15
- Project Phase 2 construction is planned for summer 2027
February 2026 Status Summary
- Bids were received on February 26 and are under review
- Project Phase 1 construction is planned for summer 2026
- Project Phase 2 construction is planned for summer 2027
January 2026 Status Summary
- Invitation to Bid release scheduled for January 16
- A mandatory pre-bid site walk was held on January 30, 2026
- Bid due date scheduled for February 26, 2026
- Progress Set of drawings and specs was received on December 2, 2025
- Project Phase 1 construction is planned for summer 2026
- Project Phase 2 construction is planned for summer 2027
Project Manager’s Notes:
- Multiple site meetings to investigate structural conditions are ongoing
December 2025 Status Summary
- ITB release scheduled for January 16, 2026
- Bid due date scheduled for February 26, 2026
- Progress Set of drawings and specs was received on December 2, 2025
- Project Phase 1 construction is planned for summer 2026
- Project Phase 2 construction is planned for summer 2027
Project Manager’s Notes:
- Multiple site meetings to investigate structural conditions are ongoing
November 2025 Status Summary
- Invitation to Bid release scheduled for January 16, 2026
- Bid due date scheduled for February 26, 2026
- Project Phase 1 construction is planned for summer 2026
- Project Phase 2 construction is planned for summer 2027
Project Manager’s Notes:
- Multiple site meetings to investigate structural conditions are ongoing
October 2025 Status Summary
- ITB release scheduled for January 13, 2026
- Bid due date scheduled for February 12, 2026
- Project Phase 1 construction is planned for summer 2026
- Project Phase 2 construction is planned for summer 2027
Project Manager’s Notes:
- Multiple site meetings to investigate structural conditions are ongoing
September 2025 Status Summary
- ITB release scheduled for October 2025
- Bid due date scheduled for November 25, 2025
- Project Phase 1 construction is planned for summer 2026
- Project Phase 2 construction is planned for summer 2027
Project Manager’s Notes:
- PRC has been contracted to design and oversee the roof replacement project
- Investigation of structural conditions took place the last week of September
August 2025 Status Summary
- ITB release scheduled for September 2025
- Bid due date scheduled for October 30, 2025
- Project Phase 1 construction is planned for summer 2026
- Project Phase 2 construction is planned for summer 2027
Project Manager’s Notes:
- Schematic design continues
July 2025 Status Summary
- ITB release scheduled for September 2025
- Bid due date scheduled for October 30, 2025
- Project Phase 1 construction is planned for summer 2026
- Project Phase 2 construction is planned for summer 2027
Project Manager’s Notes:
- Schematic design continues
June 2025 Status Summary
- ITB release scheduled for September 2025
- Bid due date scheduled for October 30, 2025
- Project Phase 1 construction is planned for summer 2026
- Project Phase 2 construction is planned for summer 2027
Project Manager’s Notes:
- Phase 1 & 2 areas of roof replacement will be determined at schematic design
- A meeting was held to discuss and confirm which areas of roof repair will be Phase 1 & Phase 2
May 2025 Status Summary
- ITB release scheduled for September 2025
- Bid due date scheduled for October 30, 2025
- Project Phase 1 construction is planned for summer 2026
- Project Phase 2 construction is planned for summer 2027
Project Manager’s Notes:
- Phase 1 & 2 areas of roof replacement will be determined at schematic design
April 2025 Status Summary
- ITB release scheduled for September 2025
- Bid due date scheduled for October 30, 2025
- Project Phase 1 construction is planned for summer 2026
- Project Phase 2 construction is planned for summer 2027
Project Manager’s Notes:
- Phase 1 & 2 areas of roof replacement will be determined at schematic design