Outdoor CTE Projects

Rendering: Outdoor Classroom, Greenhouse, and Gardens

Rendering of the outdoor classroom and greenhouse being built at Lake Oswego High School

 

October 2023

  • Greenhouse is growing multiple plants
  • Outdoor classroom has been completed and is in use
  • Landscaping is complete and irrigation has been installed
  • Raised bed planter boxes have been installed
  • Winter crops have been planted in garden area
  • Solar flower has been installed and turned on to rotate with
     the sun and put power back into the school

September 2023

Project Status:

  • Greenhouse structure has been installed and is being used by teachers
  • Outdoor classroom has been completed and is in use
  • Landscaping is complete and irrigation has been installed
  • Raised bed planter boxes have been installed
  • Solar flower has been installed and turned on to rotate with the sun and put power back into the school
  • Handrails and guardrails are complete
  • Clean-up is complete and all asphalt and curbs have been installed
  • Two electric vehicle car charging stations have been installed and are usable
  • Final inspections have been approved; Certificate of Occupancy has been issued

September 2023

Lake Oswego High School's Outdoor CTE Project
Outdoor classroom, solar flower, and greenhouse
Outdoor classroom
Planting boxes and gardens
Landscaping at Outdoor Classroom and Greenhouse

August 2023

Project Status:
Mechanical, electrical, and plumbing for greenhouse have been installed
Outdoor classroom is complete with cabinet, white board, TV monitor, and benches installed
Landscaping is finished and irrigation has been installed; additional landscape area has been installed at east end of project
Raised bed planter boxes have been installed and garden areas are being installed
Solar flower has been installed and turned on to rotate with the sun
Solar flower concrete pedestal has been completed with stone finished and anti-graffiti coating installed
Clean-up has been completed and all asphalt and curbs have been installed
Handrails and guardrails are being installed

Project Updates

Project Status:

  • Concrete curbs for the new driveway have been installed and road base gravel has been installed
  • Asphalt for the driveway is scheduled for July
  • Greenhouse structure has been completed and mechanical, electrical, and plumbing is ongoing
  • Greenhouse CMU has finished brick installed on exterior
  • Outdoor classroom structure is being installed
  • Solar flower concrete pedestal is complete. Concrete cap will arrive in July
  • Retaining wall on east side of greenhouse is complete and backfilled