Skip To Main Content

LHS Window Replacement

Remove and replace windows on north side of building.

Project Team


Dave Kruger
Project Manager

LHS building illustration showing the location of windows to be replaced

Project Updates


March 2026 Status Summary

  • Five bids were received on March 12
  • First Cascade was the lowest, responsive bidder
  • A Notice of Intent to Award was sent to all bidders on March 17
  • The contract is fully executed
  • Submittals are beginning
  • A Pre-construction meeting was held on March 24
Project Manager’s Notes:
  • Construction scheduled to start on June 15

February 2026 Status Summary

  • Invitation to Bid released February 13
  • A mandatory pre-bid site walk was held on February 27 at 4:00 p.m.
  • Bid due date scheduled for March 12
  • Project scheduled for summer 2026 construction

January 2026 Status Summary

  • ITB release is scheduled for February 13, 2026
  • A mandatory pre-bid site walk is scheduled for February 27, 2026, at 4:00 p.m.
  • Bid due date scheduled for March 12, 2026
  • Project scheduled for summer 2026 construction
Project Manager’s Notes:
  • A structural engineer site meeting is scheduled for February 29, 2026, at 3:15 p.m.

December 2025 Status Summary

  • Bid Set scheduled to be received on February 13, 2026
  • Invitation to Bid release scheduled for February 13, 2026
  • Bid due date scheduled for March 12, 2026
Project Manager’s Notes:
  • 100% Design Development delivered on December 19, 2025

November 2025 Status Summary

  • 100% design development documents planned to be delivered on December 19, 2025
  • Bid Set planned to be delivered on February 13, 2026