LHS Window Replacement
Remove and replace windows on north side of building.
Project Team
Dave Kruger
Project Manager

Project Updates
March 2026 Status Summary
- Five bids were received on March 12
- First Cascade was the lowest, responsive bidder
- A Notice of Intent to Award was sent to all bidders on March 17
- The contract is fully executed
- Submittals are beginning
- A Pre-construction meeting was held on March 24
Project Manager’s Notes:
- Construction scheduled to start on June 15
February 2026 Status Summary
- Invitation to Bid released February 13
- A mandatory pre-bid site walk was held on February 27 at 4:00 p.m.
- Bid due date scheduled for March 12
- Project scheduled for summer 2026 construction
January 2026 Status Summary
- ITB release is scheduled for February 13, 2026
- A mandatory pre-bid site walk is scheduled for February 27, 2026, at 4:00 p.m.
- Bid due date scheduled for March 12, 2026
- Project scheduled for summer 2026 construction
Project Manager’s Notes:
- A structural engineer site meeting is scheduled for February 29, 2026, at 3:15 p.m.
December 2025 Status Summary
- Bid Set scheduled to be received on February 13, 2026
- Invitation to Bid release scheduled for February 13, 2026
- Bid due date scheduled for March 12, 2026
Project Manager’s Notes:
- 100% Design Development delivered on December 19, 2025
November 2025 Status Summary
- 100% design development documents planned to be delivered on December 19, 2025
- Bid Set planned to be delivered on February 13, 2026