Skip To Main Content

LHS Window Replacement

Remove and replace windows on the north side of the Lakeridge High School building.

Project Team


Peter Miller
Project Manager

Jamie Harnish
Project Coordinator

Project Updates


September 2026 Status Summary

  • Project was completed in early September, with final painting, concrete placement, and site cleaning finished prior to the first day of school
  • Project closeout activities are currently underway, including the review of record drawings (as-builts), warranties, and operations and maintenance manuals
  • Maintenance and training with the building staff have been completed
Lakeridge High School new windows

LHS Window Replacement North Side

Lakeridge High School new windows

LHS Window Replacement North Side


August 2026 Status Summary

  • All classroom windows and common area curtainwall windows have been installed
  • Water intrusion testing has been completed with a 100% pass
  • Exterior painting has been completed
  • Interior classroom window shades are installed
  • Miscellaneous touchup paint and cleaning ongoing
  • Project was substantially completed on August 28, 2026. Minor site work and demobilization will be complete by September 4, 2026

July 2026 Status Summary

  • B Wing – Window opening prep completed; back dam has been installed. Puma Waterproofing install ongoing. Storefront install started in late July
  • F Wing – Window opening prep completed; back dam has been installed. Puma Waterproofing completed Level 2, Level 1 ongoing. Storefront install started on Level 2

June 2026 Status Summary

  • Classroom windows in the F‑Wing and B‑Wing have been removed. Waterproofing of the jambs and sills is underway, with installation of new window frames and glass scheduled for early July 
  • Demolition of the large curtain wall in the common area has begun. Installation of the new curtain wall system is planned for mid‑July
  • The exterior façade is being prepped for its new paint finish, with painting expected to begin in mid‑July
Lakeridge High School Window Replacement North Side windows covered and being worked on

Lakeridge High School Window Replacement North Side

LHS building illustration showing the location of windows to be replaced

May 2026 Status Summary

  • Main construction is scheduled to start Monday, June 15
Project Manager’s Notes:
  • Permit has been approved and issued

April 2026 Status Summary

  • First Cascade has a fully executed contract and has started the submittal review and process with various products
  • Minor window prep work will start in early May. All work will be done after school hours and only on the exterior of the building. Once an actual start date for early work is determined, school staff will be notified
  • Building permits have been approved and paid for
Project Manager’s Notes:
  • Construction is scheduled to start on June 15

March 2026 Status Summary

  • Five bids were received on March 12
  • First Cascade was the lowest, responsive bidder
  • A Notice of Intent to Award was sent to all bidders on March 17
  • The contract is fully executed
  • Submittals are beginning
  • A Pre-construction meeting was held on March 24
Project Manager’s Notes:
  • Construction scheduled to start on June 15

February 2026 Status Summary

  • Invitation to Bid released February 13
  • A mandatory pre-bid site walk was held on February 27 at 4:00 p.m.
  • Bid due date scheduled for March 12
  • Project scheduled for summer 2026 construction

January 2026 Status Summary

  • ITB release is scheduled for February 13, 2026
  • A mandatory pre-bid site walk is scheduled for February 27, 2026, at 4:00 p.m.
  • Bid due date scheduled for March 12, 2026
  • Project scheduled for summer 2026 construction
Project Manager’s Notes:
  • A structural engineer site meeting is scheduled for February 29, 2026, at 3:15 p.m.

December 2025 Status Summary

  • Bid Set scheduled to be received on February 13, 2026
  • Invitation to Bid release scheduled for February 13, 2026
  • Bid due date scheduled for March 12, 2026
Project Manager’s Notes:
  • 100% Design Development delivered on December 19, 2025

November 2025 Status Summary

  • 100% design development documents planned to be delivered on December 19, 2025
  • Bid Set planned to be delivered on February 13, 2026