Outdoor CTE Projects

October 2023

Status Summary:

  • Greenhouse is growing multiple plants
  • Outdoor classroom has been completed and is in use
  • Landscaping is complete and irrigation has been installed
  • Raised bed planter boxes have been installed
  • Winter crops have been planted in garden areas
  • Solar flower has been installed and turned on to rotate with the sun and put power back into the school

September 2023

Project Status:

  • Greenhouse structure has been installed and is being used by teachers
  • Outdoor classroom has been completed and is in use
  • Landscaping is complete and irrigation has been installed
  • Raised bed planter boxes have been installed
  • Solar flower has been installed and turned on to rotate with the sun and put power back into the school
  • Handrails and guardrails are complete
  • Clean-up is complete and all asphalt and curbs have been installed
  • Final inspections have been approved; Certificate of Occupancy has been issued
  • A divider wall has been installed in classroom D27, adjacent to the library, creating classroom D27B.
  • Final inspections have been completed

September 2023

Greenhouse interior
Inside the outdoor classroom
Planting boxes outside greenhouse

August 2023

Project Status:

  • Greenhouse structure is installed and mechanical, electrical, and plumbing has been completed
  • Landscaping has been planted and irrigation has been installed; additional landscape area has been installed at east end of project
  • Solar flower has been installed and turned on to rotate with the sun

Project Manager's Notes:

  • Substantial Completion - August 18, 2023
  • Punch lists have been provided and are being resolved
  • A divider wall is being installed in Classroom D27, adjacent to the library, creating Classroom D27B. Final inspections are being completed

August 14, 2023

The Smart Flower at Lakeridge High School is an intelligent sculpture functioning as an all-in-one solar system, generating clean energy. This sculpture and the new outdoor learning facilitity will be ready for fall classes. 

Solar flower opening to the sun

June 30, 2023

Project Status:

  • Greenhouse structure is installed and mechanical, electrical, and plumbing is being installed and connected
  • Outdoor classroom is complete with finishes being installed
  • Landscaping is being prepped and irrigation being installed; additional landscape area is being installed at east end of project
  • Solar flower is installed and being connected
  • Solar flower pedestal is complete with tile being installed on all sides
  • Clean up is ongoing with asphalt completed

Rendering: Outdoor Classroom

Rendering of an outdoor classroom for Lakeridge High School

Outdoor classroom: Under construction but making great progress!

Outdoor classroom under construction

 

Rendering: Greenhouse

Rendering of a new greenhouse for Lakeridge High School

 

Under Construction...

Newly constructed stairs that will be part of greenhouse area