Improve Accessibility

McEwan Sidewalk and Cell Tower Emergency Access project updates.

McEwan Sidewalk

Gabe Acosta, Senior Project Manager


October 2025 Status Summary:

  • McEwan sidewalks and stormwater design is complete
  • The project will include some vegetation trimming and the potential removal of some trees to permit the placement of sidewalks
  • The design currently includes cast-in-place concrete sidewalks with potential for some asphalt paving locations
  • The city has prioritized the project, and the school district has approved an increased contribution and is preparing an intergovernmental agreement

June 2025 Status Summary:

  • McEwan sidewalks and stormwater design is complete
  • The project will include some vegetation trimming and the potential removal of some trees to permit the placement of sidewalks
  • The design currently includes cast-in-place concrete sidewalks with potential for some asphalt paving locations
  • The city has prioritized the project, and the school district has proposed an increased contribution 

April 2025 Status Summary:

  • McEwan sidewalks and stormwater design is complete
  • Current construction schedule is contingent on funding partnerships and city input
  • The project will include some vegetation trimming and the potential removal of some trees to permit the placement of sidewalks
  • The design currently includes cast-in-place concrete sidewalks with potential for some asphalt paving locations

Cell Tower / Field Emergency Access

Gabe Acosta, Senior Project Manager


October 2025 Status Summary:

  • Construction is complete
  • Permits have been closed with the city

September 2025 Status Summary:

  • Construction is underway, with the concrete driveway placed
  • The new gate is being fabricated
  • The city permit will be closed once tree protection and erosion control measures are removed

August 2025 Status Summary:

  • Design is complete, and the permit is submitted to the city
  • The project will include some vegetation trimming and the potential removal of one tree to permit the placement of a concrete driveway
  • The City of Lake Oswego has been consulted regarding the project approach and feasibility
  • Tracking for completion this summer

June 2025 Status Summary:

  • Design is complete
  • The project will include some vegetation trimming and the potential removal of one tree to permit the placement of a concrete driveway
  • City of Lake Oswego has been consulted regarding the project approach and feasibility

May 2025 Status Summary:

  • Design is nearly completed and will be submitted to the city in the coming weeks
  • The project will include some vegetation trimming and the potential removal of one tree to permit the placement of a concrete driveway
  • City of Lake Oswego has been consulted regarding the project approach and feasibility

April 2025 Status Summary:

  • Design is underway and will include a concrete driveway for maintenance vehicles only
  • The project will include some vegetation trimming and the potential removal of one tree to permit the placement of a concrete driveway
  • City of Lake Oswego has been consulted regarding the project approach and feasibility