Districtwide Flooring

Remove and replace flooring in Lake Oswego High School & Lakeridge High School.

Project Team


Peter Miller & Sam Blohn
Project Managers

Jamie Harnish
Project Coordinator

Project Updates


Lake Oswego High and Lakeridge High Flooring Replacement

September 2026 Status Summary:

  • Substantial completion of Phase 1was issued August 28
  • Phase 1 closeout is complete, pending O&M and key turnover
  • Contractor will order Phase 2 material in December
  • Retainage is still being held
  • Project managers are reviewing Phase 2 scope with school staff to ensure alignment
  • Phase 2 will cover all classrooms and some additional spaces
LHS cafeteria new flooring

Lakeridge High School Flooring Replacement - Commons /Cafeteria


Lake Oswego High and Lakeridge High Flooring Replacement

August 2026 Status Summary:

  • All rubber flooring and carpet have been installed for Phase 1 - Summer 2026 scope
  • Punch list and back-punch work has been completed
  • Maintenance and training sessions from the flooring and carpet manufacturers have been completed with the building engineers
  • Summer 2026 project closeout has begun
  • Phase 2 will begin during the 2027 summer break

Lake Oswego High School Flooring Replacement

July 2026 Status Summary:

  • Level 1: Carpet has been installed in office areas
  • Tile has been installed throughout the entire first floor
  • Cove base has been installed throughout the entire first floor
  • 2 stairwells have had carpet removed, and concrete has been sealed
  • Level 2: Flooring Installation has been completed on the entire second floor of the building
  • Punchlist: Contractor started cleaning the building July 27
  • Punchlist will happen in early August

Lakeridge High School Flooring Replacement

July 2026 Status Summary:

  • Level 1-Sector H - F Wing - Flooring & base install completed
  • Level 2-Sector A - Admin - Carpet and base install completed. Office furniture move the week of August 3
  • Sector B - Auditorium - Carpet install 100% complete. Lobby floor demo complete. Slab prep ongoing
  • Sector C - Music - Flooring 95% complete. Rubber base started
  • Sector D - Cafeteria -  Flooring and rubber base install is complete
  • Sector E - B Wing - Flooring and base install completed
  • Sector F - North Rotunda - Ardex floor leveler installed 95%
  • Sector G - South Rotunda - Ardex floor leveler installed 50%
  • Sector H - F Wing - Flooring and base install completed
  • Lower Level Rotunda-Carpet and base install completed
  • Library - Carpet and base install completed. Furniture, books, and shelves install is completed

Lake Oswego High School Flooring Replacement

June 2026 Status Summary:

  • LOHS Flooring Contractor is being held up on install due to product being delivered late. Delivery is expected by the first week of July
  • East Side: Contractor began work on the east side of the building, working their way west
  • Sectors A, B, and C on floors 1 and 2: Flooring demo and prep complete 
  • Sectors D and E, level 1: Demolition and prepping in process 
  • Sectors A and B, levels 1 and 2, as well as Sector C, level 2: Tile flooring installed 
  • Sector C:  Carpet was removed under two staircases, which was not in the scope of work. These areas will be added to the scope and will be polished concrete or tile flooring

Lakeridge High School Flooring Replacement

June 2026 Status Summary:

  • B‑Wing: Corridor carpet has been removed, and floor grinding is complete. Floor‑leveling compound installation begins in early July
  • Cafeteria: Approximately 75% of the existing flooring has been removed. Floor grinding and slab preparation are currently underway
  • Admin Area: Carpet and wall base removal is in progress. Floor preparation is scheduled to begin in early July
  • F‑Wing (Upper & Lower Levels): Corridor carpet has been removed, and floor grinding is complete. Floor‑leveling compound installation begins in early July
  • Library: Carpet removal and floor grinding are complete. Floor‑leveling compound installation begins in early July
  • Lower‑Level Rotunda: Carpet removal and floor grinding are complete. Floor‑leveling compound installation begins in early July
  • Main Rotunda: Corridor carpet has been removed, and floor grinding is complete across roughly 75% of the common area, Floor‑leveling compound installation begins in early July

May 2026 Status Summary:

  • Phase 1 flooring replacement begins June 15

Project Manager’s Notes:

  • Contractor had site walks with all subcontractors at both high schools
  • Site logistics plans are being coordinated
  • Contractor will mobilize on site on June 15
  • Demolition will begin on June 16
  • Lake Oswego High will have a single contractor for demo and installation
  • Lakeridge High will have a separate demo & install contractor

April 2026 Status Summary:

  • Contract and Notice to Proceed with conditions were sent on April 21
  • A Pre-construction meeting was held on April 24

Project Manager’s Notes:

  • Flooring submittals are being processed
  • 2 coordination site walks have been held
  • Floor removal and prep for both high schools will begin on June 15

March 2026 Status Summary:

  • Additional scope and additional subfloor preparation was added to the project following site investigations. The budget has been adjusted
  • Three bids were received on March 18
  • Rubenstein’s Contract Carpet LLC was the lowest responsive bidder
  • A Notice of Intent to Award was sent to all bidders on March 27
  • A Pre-construction meeting is scheduled for April 1

February 2026 Status Summary:

The high school flooring replacement project will be a two-phase, two-summer project. The first phase, beginning in June 2026, will include replacing carpet with hard-surface flooring in corridors and hallways. The auditoriums, administration offices, and counseling offices will receive new carpeting, and the cafeteria flooring will be replaced with a new hard-surface floor. The second phase will begin in June 2027 and include replacing the carpet in classrooms and the library at both high schools. 

Both phases went out to bid on February 13, with bids due March 18. 


January 2026 Status Summary:

The high school flooring replacement project will be a two-phase, two-summer project. The first phase, beginning in June 2026, will include replacing carpet with hard-surface flooring in corridors and hallways. The auditoriums, administration offices, and counseling offices will receive new carpeting, and the cafeteria flooring will be replaced with a new hard-surface floor. The second phase will begin in June 2027 and include replacing the carpet in classrooms and the library at both high schools. 

Both phases will go out to bid on February 13, with bids due March 18.


December 2025 Status Summary:

The high school flooring replacement project will be a two-phase, two-summer project. The first phase, beginning in June 2026, will include replacing carpet with hard-surface flooring in corridors and hallways. The auditoriums, administration offices, and counseling offices will receive new carpeting, and the cafeteria flooring will be replaced with a new hard-surface floor. The second phase will begin in June 2027 and include replacing the carpet in classrooms and the library at both high schools.