Districtwide FF & E
Replace classroom furniture at Hallinan Elementary School and Westridge Elementary School.
Project Team
Daniel Camacho & Samuel Blohn
Project Manager
Project Updates
June 2026 Status Summary:
- Site visits before furniture delivery are scheduled for July 6
Project Manager’s Notes:
- Furniture will be delivered in two shipments: July 7 and July 20
- Installation of furniture will begin on July 20
May 2026 Status Summary:
- Insidesource’s purchase order has been processed
Project Manager’s Notes:
- Furniture will be delivered in two shipments: July 7 and July 20
- Installation of furniture will begin on July 20
- Insidesource will coordinate site walks at both schools before installation
April 2026 Status Summary:
- Contracts have been distributed and fully signed
- Notice to Proceed with conditions was sent out on April 9
- Pre-order meeting was held on April 16
Project Manager’s Notes:
- Furniture submittals have been approved
- Final count of furniture items has been provided to Insidesourc
- The furniture order will be placed during the first week of May
March 2026 Status Summary:
The Westridge and Hallinan furniture replacement project is scheduled for the summer of 2026. Beginning in June, the project will involve replacing all student classroom furniture, including desks, tables, and chairs.
Three bids for the project were received on March 10. Insidesource submitted the lowest bid, and the contract is currently moving through the approval process. The team is coordinating with both schools, and the furniture order is expected to be released in mid-April.
February 2026 Status Summary:
The Westridge and Hallinan furniture replacement project is scheduled for the summer of 2026. Beginning in June, the project will involve replacing all student classroom furniture, including desks, tables, and chairs.
The project went out to bid on February 2, with bids due March 10.