Skip To Main Content

LORAC Project Updates

LORAC aerial view of building

May 2025


Status Summary:
  • Interior punchlist corrections are nearly complete
  • Exterior punchlist corrections and miscellaneous work continue
  • The overall schedule remains in Requires Resolution since a revised schedule has not been approved. The City has indicated that they may be assessing damages to the contractor for loss of use due to the project not being completed on time
  • The project is substantially complete, and temporary occupancy has been granted for use of the office spaces, gym, and workout rooms

April 2025


two workers finishing the LORAC pool entrance
LORAC pool
Status Summary:
  • Interior punchlist corrections are nearly complete
  • Exterior punchlist corrections and miscellaneous work continue
  • The overall schedule remains in Requires Resolution since a revised schedule has not been approved. The City has indicated that they may be assessing damages to the contractor for loss of use due to the project not being completed on time
  • The project is substantially complete, and temporary occupancy has been granted for use of the office spaces, gym, and workout rooms

March 2025


lorac building with blue skies
lorac pool
LORAC pool slide
Status Summary:
  • Interior finishes in the offices, workout rooms, gym, and locker areas are nearly completed, and the contractor is preparing for punchlist inspections
  • Exterior finishes for the natatorium building are nearing completion
  • Exterior finishes nearing completion at the main entry, workout areas, and gym
  • Sitework is ongoing - curbs are being installed, and asphalt is being placed
  • The overall schedule remains in Requires Resolution since a revised schedule has not been approved. The schedule for completion is reporting mid-April. The City has indicated that they may be assessing damages to the contractor for loss of use due to the project not being completed on time
  • The project will require review periods by the city and health department, the city may grant temporary occupancy for portions of the building to allow staff access, and the start of operation

February 2025


aerial view of LORAC construction
LORAC showers
LORAC gym
Status Summary:
  • Interior finishes in the offices, workout rooms, gym, and locker areas are nearly completed and the contractor is preparing for punchlist inspections
  • Exterior finishes for the natatorium building continue
  • Exterior finishes nearing completion at the main entry, workout areas, and gym
  • Sitework is ongoing - curbs are being installed, and asphalt is being placed
  • The overall schedule remains in Requires Resolution since a revised schedule has not been approved. The schedule for completion is reporting mid March. The City has indicated that they will likely be assessing damages to the contractor for loss of use due to the project not being completed on time
  • The project will require review periods by the city and health department, the city may grant temporary occupancy for portions of the building to allow staff access, and the start of operation

January 2025


aerial view of rec center parking lot and building in final stages of construction
LORAC pool under construction
LORAC gym under construction
Status Summary:
  • Interior finishes in the offices, workout rooms, gym, and locker areas continue
  • Exterior finishes for the natatorium building continue
  • Exterior finishes nearing completion at the main entry, workout areas, and gym
  • Sitework is ongoing - curbs are being installed, and asphalt is being placed
  • The overall schedule remains in Requires Resolution since a revised schedule has not been approved. The schedule for completion is reporting mid March. The City has indicated that they will likely be assessing damages to the contractor for loss of use due to the project not being completed on time

December 2024


LORAC pool slide
LORAC aerial view of construction
Status Summary:
  • Interior finishes in the offices, workout rooms, gym, and locker areas continue
  • Exterior finishes for the natatorium building continue
  • Exterior finishes are continuing around Building A, including offices, entry, gym, and workout rooms
  • Sitework is ongoing - curbs are being installed, and the site is being prepared for asphalt
  • The overall schedule remains in Requires Resolution since a revised schedule has not been approved. Following numerous project team meetings, the contractor has provided a schedule that shows completion of the project in early March 2025. The City has indicated that they will be assessing damages to the contractor for loss of use due to the project not being completed on time

September 2024


LORAC aerial
LORAC pool under construction
Status Summary:
  • Interior finishes in the offices, workout rooms, gym, and locker areas continue
  • Exterior masonry of the natatorium building continues
  • Exterior finishes are continuing around Building A, including offices, entry, gym, and workout rooms
  • Sitework is ongoing
  • The overall schedule is in caution due to slow progress with the pre-engineered building. We have not yet received a formal claim, but the contractor has indicated that they anticipate completion sometime in January

May 2024


Aquatic center under construction- aerial view
Aquatic center under construction
Aquatic center under construction
Aquatic center under construction - aerial view
Aquatic center under construction - aerial view
Aquatic center under construction - aerial view
Aquatic center under construction
Aquatic center under construction
Aquatic center under construction
Aquatic center under construction
Aquatic center under construction - inside
Aquatic center under construction - looking out windows
Aquatic center under construction - aerial view

February 2024


Aquatic Center: January 2024
Aquatic Center: January 2024
Aquatic Center: January 2024
Aquatic Center: January 2024
Aquatic Center: January 2024

February 16, 2024

Aquatic center aerial
Aquatic center aerial
Aquatic center aerial
Aquatic center aerial
Aquatic center aerial
Aquatic center aerial
Aquatic center aerial
Aquatic center aerial
Aquatic center aerial
Aquatic center aerial

January 22, 2024

Aquatic Center: January 22, 2024
Aquatic Center: January 22, 2024
Aquatic Center: January 22, 2024
Aquatic Center: January 22, 2024
Aquatic Center: January 22, 2024
Aquatic Center: January 22, 2024
Aquatic Center: January 22, 2024
Aquatic Center: January 22, 2024
Aquatic Center: January 22, 2024
Aquatic Center: January 22, 2024
Aquatic Center: January 22, 2024

December 2023

Project Status:

  • Wall framing continued through the month of December
  • District and City are working with the cell tower operator
     to coordinate relocation of conduits at the Overlook access
  • The Natatorium building is in production
  • The overall schedule is indicating a delay; the contractor
     has submitted an updated schedule. The updated schedule
     suggests a completion time in late fall 2024. The project
     team has not granted an extension at this time; project
     team currently evaluating the recent schedule

November 2023

 Project Status:

  • Wall framing will continue through the month of December
  • District and City are working with the cell tower operator to coordinate relocation of conduits at the Overlook access
  • The Natatorium building is in production
  • The overall schedule is indicating a delay; the contractor has submitted an updated schedule. The updated schedule suggests a completion time in late fall 2024. The project team has not granted an extension at this time; project team currently evaluating the recent schedule

November 30, 2023

Aerial Photo of Aquatic Center Project: 11.30.23
Aerial Photo of Aquatic Center Project: 11.30.23
Aerial Photo of Aquatic Center Project: 11.30.23
Aerial Photo of Aquatic Center Project: 11.30.23
Aerial Photo of Aquatic Center Project: 11.30.23
Aerial Photo of Aquatic Center Project: 11.30.23
Aerial Photo of Aquatic Center Project: 11.30.23
Aerial Photo of Aquatic Center Project: 11.30.23
Aerial Photo of Aquatic Center Project: 11.30.23
Aerial Photo of Aquatic Center Project: 11.30.23

November 16, 2023

Aerial photo of Aquatic Center construction
Aerial photo of Aquatic Center construction
Aerial photo of Aquatic Center construction
Aerial photo of Aquatic Center construction
Aerial photo of Aquatic Center construction
Aerial photo of Aquatic Center construction
Aerial photo of Aquatic Center construction
Aerial photo of Aquatic Center construction

October 2023

Project Status:

  • Wall framing continues and framing will be ongoing during the month of November
  • District and City are working with the cell tower operator to coordinate relocation of conduits at the
    Overlook access
  • The overall schedule is indicating a delay; the contractor has submitted an updated schedule. The updated schedule suggests a completion time in late fall 2024. The project team has not granted an extension at this time; project team currently evaluating the recent schedule

October 24, 2023

Aerial photo of Aquatic Center Project: October 24, 2023
Aerial photo of Aquatic Center Project: October 24, 2023

September 2023

Project Status:

  • Wall framing has begun and visible structure will emerge during the month of October
  • Temporary sidewalks have been installed along Stafford Road
  • District and City are working with the cell tower operator to coordinate relocation of conduits at the Overlook access
  • The overall schedule is indicating a delay; however, the contractor has not yet submitted a claim for additional time and continues to try to make up time

September 20, 2023

Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23
Aerial Photo of Aquatic Center Project: 9.20.23

August 2023

Project Status:

  • The contractor continues with footings and floor slabs. Framing materials are being delivered and framing will begin in early September
  • District and City are working with the cell tower operator to coordinate relocation of conduits at the overlook access
  • The overall schedule is indicating a delay; however, the contractor has not yet submitted a claim for additional time and continues to try to make up time

June 30, 2023

Project Status:

  • The contractor continues with mass excavation and footings are being formed
  • The overall schedule is indicating a delay, however, the contractor has not yet submitted a claim for additional time and continues to try to make up time
  • A requirement for relocating a water main in Stafford Road has been determined through City permitting review. This will be a change to the contractor’s scope of work

June 14, 2023

Construction Site for future Aquatic Center
Construction Site for future Aquatic Center
Construction Site for future Aquatic Center

Update: September 8, 2022

The Development Review Commission hearing was held in August. The hearing was continued at the request of Stafford Hamlet. The hearing continued on September 7, where is was approved 6-0. The decision will become final following the appeal period.

Project Updates

100% Design Documents have been received by the project team and the project will be moving into construction documentation. The City will be publishing a RFQ (Request for Qualifications) for prequalification of contractors for the project. 

In May and early June 2021, public surveys with close to 300 responses showed a desire for a large facility, with clear preferences for:

  • designs allowing the largest pool capacity
  • plenty of space for recreational lap swimming
  • a competition pool with the swim direction the same for both practice and meets
  • adequate space for fitness classes
  • adequate parking for all uses and events

Lake Oswego Recreation & Aquatics Center IGAs Authorized by City and LOSD

The Lake Oswego School Board authorized LOSD's Intergovernmental Agreements (IGAs) with the City of Lake Oswego relating to the construction and use of the Lake Oswego Recreation and Aquatics Center (LORAC) that will be constructed on the City's municipal golf course.

LOSD and the City entered into a Memorandum of Understanding (MOU) dated July 9, 2020, that outlined the general parameters of how the City and LOSD would share in the design, construction, and operations of the new LORAC building that is antipated to open in late calendar year 2023, including allocations of costs for those purposes. As the MOU only outlined general parameters, the IGAs detail the rights and responsibilities of each party, with a separate IGA for the construction that will lapse when construction is completed, and an IGA for the operations and use of the competitive pool that, with no changes or extensions, will terminate on June 30, 2043.

The Construction IGA addresses the mutually agreed upon facility including: 25-yard stretch competition swimming pool; warm water recreation pool; dry activity and exercise rooms; parks and recreation classrooms; parks and recreation offices; and cardio/weight room and gymnasium.

This agreement also addresses: equal allocation of all direct costs for the project up to a total of $30 million ($15 million each); methodology for allocating savings or additional costs; contracting responsibility and methodology; and allocation of internal project management responsibilities.

The Use IGA addresses the parties' share of operating costs and subsidies; responsibilities and funding for maintenance, repair, and replacement; and priority and scheduling of use of the various elements within the center. 

Document Viewer